NEW QUESTION 20
How many people are typically into an ART?

  • A. 30 to 40
  • B. 250 to 300
  • C. 10 to 25
  • D. 50 to 125+

Answer: D

 

NEW QUESTION 21
Which component of the Continuous Delivery Pipeline is the ability to make value available to customers all at once, or in a staggered fashion based market and business needs?

  • A. Continuous Exploration
  • B. Continuous Integration
  • C. Release On Demand
  • D. Continuous Deployment

Answer: C

 

NEW QUESTION 22
Which of the following are true for the System demo?

  • A. It happens once per PI, at the end of the PI
  • B. Architectural Runway work in process is scaffolded and toggled
  • C. It is not mandatory to have all the functionalities tested before the demo
  • D. Features are functionally complete or "toggled" so as not to disrupt demonstrable functionality

Answer: B,D

 

NEW QUESTION 23
How long at a maximum is Iteration Planning?

  • A. 2 hours
  • B. 1 day
  • C. 6 hours
  • D. 4 hours

Answer: D

 

NEW QUESTION 24
There are Ten Core Competencies of Business Agility

  • A. FALSE
  • B. TRUE

Answer: A

 

NEW QUESTION 25
Where are the improvement items identified during the Iteration retrospective stored?

  • A. Database
  • B. Team backlog
  • C. Improvements sheet
  • D. Program Backlog

Answer: B

 

NEW QUESTION 26
Who acts as the Customer for Developer requests?

  • A. Epic Owner
  • B. Business Owner
  • C. Scrum Master
  • D. Product Owner

Answer: D

 

NEW QUESTION 27
Architectural Runway includes existing code, hardware components, business infrastructure, etc. that enable near-term business features.

  • A. TRUE
  • B. FALSE

Answer: A

 

NEW QUESTION 28
The Business can change priorities during the Iteration

  • A. FALSE
  • B. TRUE

Answer: A

 

NEW QUESTION 29
Which of the below is not part of the Continuous Delivery Pipeline?

  • A. Continuous Exploration
  • B. Continuous Integration
  • C. Continuous Deployment
  • D. Continuous Testing

Answer: D

 

NEW QUESTION 30
Who directs the Agile team?

  • A. Scrum Master
  • B. Project Manager
  • C. Product Owner
  • D. The Agile Team is self-organizing

Answer: D

 

NEW QUESTION 31
Agile Product Delivery is one of the Core Competencies of Business Agility.

  • A. TRUE
  • B. FALSE

Answer: A

 

NEW QUESTION 32
Which 2 of the below are common techniques for splitting stories into smaller ones?

  • A. WSJF
  • B. Business Rule variation
  • C. High priority
  • D. Simple or Complex
  • E. INVEST

Answer: B,D

 

NEW QUESTION 33
Which of the following is not 1 of the 3Cs of good user stories?

  • A. Conversation
  • B. Card
  • C. Continuation
  • D. Confirmation

Answer: C

 

NEW QUESTION 34
Scrum and Kanban cannot be used together - either of the two needs to be chosen to be implemented.

  • A. FALSE
  • B. TRUE

Answer: A

 

NEW QUESTION 35
Which of the following is the recommended approach to create T-shaped skills on the ART?

  • A. Cross-training
  • B. rotating team members between different teams
  • C. Pair-programming
  • D. All of the above

Answer: D

 

NEW QUESTION 36
Program Agility is one of the Core Competencies of Business Agility.

  • A. FALSE
  • B. TRUE

Answer: A

 